Rehabilitation of the T'PLA reservoir is delayed/ The tender was canceled twice and still no winner

2026-01-11 15:20:00, Denoncim CNA

Rehabilitation of the T'PLA reservoir is delayed/ The tender was canceled

The procurement procedure for the rehabilitation of the T'PLA water reservoir in the Municipality of Tropoja, with a limit fund of 27,486,280 lek excluding VAT, continues to be accompanied by serious suspicions of legal violations and intentional delay. This concerns the tender with reference REF-67031-10-29-2025, published on the Open Procurement platform.

Rehabilitation of the T'PLA reservoir is delayed/ The tender was canceled
Tender for the rehabilitation of the T'PLA watershed

During 2025, this procedure was re-announced three times. The tender was not awarded to contractors with close ties to the mayor, and it was canceled twice at the evaluation stage, claiming that the legal basis was lacking.

Rehabilitation of the T'PLA reservoir is delayed/ The tender was canceled
Government Fund for the T'PLA Watershed

First cancellation

The tender was first announced on 15 July 2025, with bids opened on 4 August 2025. The procedure was cancelled according to Bulletin No. 46, dated 25 August 2025, on the grounds that “unforeseen circumstances and the solvency of the contracting authority have changed”.
However, this argument is refuted by the fact that the procedure was re-announced with the same limited fund, while the financing was guaranteed by the Central Government with VKM No. 128, dated 28.02.2025, for the years 2025–2026. 7 companies participated in this phase.

Rehabilitation of the T'PLA reservoir is delayed/ The tender was canceled
Broken water collector

Second cancellation

The procedure was re-announced on September 26, 2025, with bids opening on October 13, 2025, but was canceled again with the argument that the tender documents “contained significant errors or deficiencies”. According to verifications, the standard documents, the fund and the criteria had not undergone any changes, raising suspicions of unjustified cancellation. Seven companies also participated in this phase: Nika Sh.pk, Cara Sh.pk, Shendelli Sh.pk, ASI Invest Sh.pk, Shpresa Al Sh.pk, Griald Sh.pk and Florida Sh.pk

The third procedure and the delay in announcing the winner

The tender was announced for the third time on October 30, 2025, with bids opening on November 14, 2025. The evaluation was carried out more than a month later, on December 12, 2025, in violation of the legal deadlines for public procurement.

The economic offers were the same companies as in the second phase, with offers as follows:

Ergi Sh.pk with 16,180,699 lek
Nika Sh.pk with 16,738,890 lek
Florida Sh.pk with 16,821,053 lek
Griald Sh.pk with 16,922,115 lek
ASI Invest Sh.pk with 16,998,828 lek
Shendelli Sh.pk – 17,160,308 lek
Colombo LTD – 19,874,211 lek

Rehabilitation of the T'PLA reservoir is delayed/ The tender was canceled
Final assessments

Kompania Ergi Sh.p.k, e renditur e para, u njoftua për dorëzimin e dokumentacionit dhe më 16 dhjetor 2025 dorëzoi të gjitha dokumentet, identike me ato të ngarkuara në sistemin elektronik. Megjithatë, Bashkia Tropojë vijon të mos shpallë fituesin dhe të mos lidhë kontratën, në kundërshtim me ligjin, pavarësisht se fondi është i garantuar nga qeveria qendrore.

Rehabilitation of the T'PLA reservoir is delayed/ The tender was canceled
Kompania e renditur në vendin e parë

Investim jetik për banorët

Ujëmbledhësi në Tpla në Njësinë Administrative Fierzë është i vetmi burim vaditjeje për fshatin dhe njëkohësisht shërben si mbrojtje nga përmbytjet. Në vitin 2022, argjinatura e tij u hap nga Bashkia Tropojë me pretendimin e rrezikut për shembje, duke e dëmtuar rëndë objektin.

Rehabilitation of the T'PLA reservoir is delayed/ The tender was canceled
Gjendja e kolektorit

Akuza dhe heshtje institucionale

Zvarritja e këtij investimi i atribuohet kryetarit të Bashkisë Tropojë, Rexhë Byberi dhe nënkryetares Zyra Islamaj, të cilët janë të akuzuar dhe në proces gjyqësor në GJKKO për shpërdorim detyre dhe korrupsion pasiv.

Ndërkohë që qeveria ka deklaruar se më herët Bashkia Tropojë ishte e bllokuar për shkak të mungesës së kryetarit, aktualisht drejtuesit janë në detyrë, por kontrata nuk lidhet dhe investimi mbetet peng i zvarritjeve, në dëm të drejtpërdrejtë të banorëve të zonës./CNA